THE DIFFERENT STEPS OF THE CONSTRUCTION
About 4 weeks are enough, between the first idea and the installation of your tree house. Contact us to get a free expertise of your tree house project.
1. Diagnostic of your tree (recommended)
In all regions, there are independent foresters who can realize the diagnostic of your host tree. It should cost you between 250 Euros and 400 Euros. BubbleTree refunds you a part of this expense when the tree house construction will start.
2. The manufacture of your tree house
We manufacture your BubbleTree according to your specific demand (way of access and options). 3 to 5 weeks are enough to realize your dream.
3. The installation of your tree house
On average, the installation of your tree house lasts 2 to 4 days. Contact us to get a free expertise of your project.